Status of Cost Reports under ERP Systems- Implementation

Could you please say what are the other Reports completed from KPMG end with respect to our given list.
So far as I know, for costing,

  1. Renata Inventory Valuation (only Ending balances)--> Tested for results but not in my format (As Beg. Balance--->Receipts-->Issues---->Ending Balance)
  2. Product Cost Sheet (consolidated) NOT in Formulation level which we required
  3. Yield Report

They have completed following reports which were not given by us but internally necessary for other reports and accounting to be updated.
  1. Resource Usage Report
  2. Resource Cost Update

They have completed following reports which was not tested for Reference/Data constraints:

  1. MDR Report ---> Detail list is missing, so I can not comment as to whether it generates correct figures
All other costing reports are deferred to post GoLive